AI data centers turn to jet turbines and diesel; GE Vernova orders rise 33% in 2025
Data center operators are installing aircraft-derived turbines and diesel generators to bypass long grid-connection waits. In December 2025, GE Vernova said orders for its aircraft-based units rose 33% in the first nine months of 2025, while Cummins delivered more than 39 GW and doubled capacity. BNP Paribas estimates Meta's Ohio behind-the-meter power at $175/MWh, roughly twice typical industrial rates.